Quick answer: Version 1.1 of the UAE Electronic Invoicing Guidelines, published by the Ministry of Finance on 1 June 2026, explains how to show retention in e-invoices. At each progress or milestone billing, the e-invoice shows only the net amount payable after retention, with 5% VAT on that net amount. When the retention is released, you issue a separate electronic tax invoice for it, with its own VAT.
Retention is common in construction, contracting, and real estate development in the UAE. The client holds back part of each payment until the project is finished or the defects liability period ends.

Before e-invoicing, it wasn't always clear how this should appear in a structured invoice. Appendix 5 of Version 1.1 answers that question. This guide explains the rule, shows it in numbers, and lists what to set up in your ERP.

What is retention billing?

Retention is a part of each progress payment, often 5% or 10%, that the client holds back under a construction or development contract. The contractor receives it later, usually at practical completion or at the end of the defects liability period.

Retention protects the client if work needs fixing after completion. For the contractor, it means that part of the money for each stage arrives months or even years later.

For tax purposes, this creates a timing question. Should the invoice for each stage show the full value, or only what's actually paid now? For e-invoices, Version 1.1 gives a clear answer.

What changed in Guidelines Version 1.1?

The Ministry of Finance published the first UAE Electronic Invoicing Guidelines on 23 February 2026. Version 1.1 followed on 1 June 2026, with two new appendices.
Version 1.1 didn't change who must comply or when. Businesses with revenue of AED 50 million or more still go live on 1 January 2027, and other businesses on 1 July 2027.

How should retention appear on an e-invoice?

Under Appendix 5, an e-invoice for a progress or milestone billing reflects only the net amount actually payable at that stage, with VAT applied to that net figure.

When the retained amount becomes payable, for example at the end of the defects liability period, a separate electronic tax invoice is issued for it. That invoice carries its own VAT.

Some advisers also recommend a separate commercial document for each milestone that shows the total milestone value and the retention deducted. It isn't the e-invoice itself, but it keeps the full picture clear for both parties and for any later FTA review.

A full project example in numbers

The example at the top of this page shows one milestone. Here's a full contract worth AED 3,000,000, billed in three equal milestones, with 10% retention and 5% VAT.
Across all four invoices, VAT is charged on the full AED 3,000,000. The only difference is timing: VAT on the retention is charged when the retention is released, not at each milestone.

When is VAT charged on retained amounts?

On the e-invoice, VAT on retained amounts appears only on the separate invoice issued when the retention is released. The progress e-invoices carry VAT on the net amounts payable at each stage.

This matches how many contractors already handle retention under UAE VAT law. If your contracts have unusual payment terms, check the VAT timing with your tax adviser before you set up your e-invoicing templates.

How do advance payments work?

Appendix 5 also covers advance payments, which are common on the same projects. A tax invoice is issued when the advance payment is received.

The advance invoice and the final invoice for the same supply must be linked. This lets the FTA trace how the advance was settled against the full value of the work.

In practice, your ERP needs to store which advance belongs to which contract or project, and carry that reference into the final invoice. Check this during testing, not after go-live.

Do you need to change how you bill?

For most businesses, no. Advisers including PwC and Crowe describe Version 1.1 as a clarification of how to comply, not a redesign of retention structures.

Existing VAT-compliant practices can continue: invoice net of retention at interim stages, and invoice the retention separately on release. What does need attention is making sure your ERP produces those invoices correctly in the PINT AE format.

How does this affect subcontractors and main contractors?

Retention runs through the whole supply chain. The same company is often a supplier to the developer and a buyer from its subcontractors.
If you're on the receiving side, your accounts payable team should know what these invoices look like. They also need a way to match release invoices to the original contracts, sometimes years later.

What should you set up in your ERP?

Most construction and real estate businesses already track retention. The work is making sure that tracking flows correctly into e-invoices. Check these points with your finance team and your provider:
  • Progress invoices calculate VAT on the net amount after retention, not on the full milestone value.
  • Retained amounts are tracked per project, so the release invoice can be issued on time.
  • The release of retention creates its own separate e-invoice with its own VAT.
  • Advance payment invoices are linked to the final invoice for the same supply.
  • Each invoice carries a clear project or contract reference.
  • Test invoices for each of these cases are run before go-live.

Common mistakes to avoid

These mistakes come up most often when contractors move retention billing to e-invoices:

How long must project records be kept?

According to Appendix 4 of Version 1.1, e-invoicing records generally must be kept for 5 years, and real estate records for 7 years. An additional 4 years applies if there is an FTA audit or dispute.

Long projects make this important. A release invoice issued years after the first milestone must still be traceable to the original contract and invoices. Appendix 4 also allows storage in the cloud, including outside the UAE, if the FTA can retrieve the records when needed.

Key takeaways

  • Point 1

    Version 1.1 of the UAE Electronic Invoicing Guidelines, dated 1 June 2026, added Appendix 5 on advance payments and retention.
  • Point 2

    A progress e-invoice shows only the net amount payable after retention, with VAT on that net amount.
  • Point 3

    When retention is released, a separate electronic tax invoice is issued for it, with its own VAT.
  • Point 4

    Across the whole contract, VAT is charged on the full value. Only the timing differs.
  • Point 5

    Advance payment invoices must be linked to the final invoice for the same supply.
  • Point 6

    For most businesses, Version 1.1 clarifies existing VAT-compliant practice rather than replacing it.
“
OFFICIAL SOURCES:

UAE Electronic Invoicing Guidelines, Version 1.1, Ministry of Finance, 1 June 2026, Appendices 4 and 5
Ministerial Decision No. 243 of 2025
Ministry of Finance e-invoicing portal: mof.gov.ae

This article explains the Guidelines in general terms and is not tax advice. Check your specific contracts with your tax adviser.

Frequently Asked Questions

Under Appendix 5 of the UAE Electronic Invoicing Guidelines, Version 1.1, an e-invoice for a progress or milestone billing can show only the net amount payable at that stage, after the retention is deducted, with VAT applied to that net amount. When the retained amount becomes payable, a separate electronic tax invoice is issued for it, with its own VAT.

How Aiverix handles retention and advance billing

Aiverix is an FTA-accredited service provider and certified Peppol Access Point based in Dubai. We set up retention and advance billing during implementation, not after the first rejected invoice.

• Checks every invoice before it's sent, including the VAT calculation on net amounts.
• Supports separate release invoices and links between advance and final invoices.
• Tests your real project invoice types, including retention and advances, before go-live.
• Ready connections for Odoo, Xero, Zoho, SAP, Oracle, Microsoft Dynamics, and Tally.

See all features on the Aiverix e-invoicing page, or book a free 30-minute call and get a go-live plan for your business.

Related guides:
UAE E-Invoicing: Complete Compliance Guide
E-Invoicing Integration with SAP and Oracle in the UAE
Aiverix e-invoicing platform

All Articles Now Published